Municipal2024

Kisumu Central Water Hub

Kisumu, Kenya

50,000+ People Served

Challenge

The central municipal pumping station needed more stable pressure and continuity across a distribution network serving a large urban catchment — without long outages during upgrade.

Approach

We designed a synchronized multi-pump duty/assist arrangement with clearer control logic for peak and off-peak demand, then commissioned staged cutovers so the network stayed live during the transition.

Outcome

Pressure stability improved across the served zones, supporting reliable supply for an estimated 50,000+ people connected to the hub’s distribution footprint.

Equipment & scope

  • Synchronized multi-pump station packages
  • Controls and handover documentation for operators

Project photos